The City of Hamilton has a contract with Cornell Construction Ltd. to perform preventative maintenance on the following roads as called for under contract C15-46-15.  the Surface Treatment program contributes to reduced maintenance costs, dust mitigation and extended road lifecycle expectancy.  Construction is scheduled to commence on or about June 15, 2015, with a completion date of August 31, 2015, weather permitting.

Street Name                       From                          To 

Leeming Road                                  Hwy #6                                 Ferris Road

Eighth Road East                             Ridge Road                         850 S of Ridge Road

Purdy Crescent                                 Mud Street                         East Townline Road

Tenth Road East                              Highland Road East         Mud Street East

Cemetery Road                                 Fletcher Road                    Hwy #56

Read More