The area of Twenty Rd, from Upper James to Glancaster Road will be re-surfaced this summer. The following is the timetable for the works to be completed:
- Installation of Culvert will be completed on July 04, 2014.
- Ditching is scheduled to be completed during week of July 21, 2014.
- Resurfacing is scheduled to be completed during week of July 28, 2014.
Let’s keep our fingers crossed for good weather.